On April 27, 2005 DÜCHTING PUMPEN received an order from Austrian Energy & Environment, Graz for the delivery of Absorber Recycle and Process Pumps for the Power Plant Ruien in Belgium.
After 1997 it is the second plant we equipped with SICcast® Pumps for the utility Electrabel N.V. A main decision for getting this order was the very good experiences with our pumps at the Power Plant Langerlo (Noell_KRC).
To be able to reach the required operating data with a direct drive, Düchting developed a new pump model.
| Technical Data: |
| Pump Type: |
ROWA-MCC 800-950 |
|
|
| Capacity: |
8300 m3/h |
|
|
| Delivery Head: |
17 … 21 m |
|
|
Overview |